Preface | p. iii |
Figures | p. ix |
Tables | p. xi |
Summary | p. xiii |
Acknowledgments | p. xix |
Abbreviations | p. xxi |
Introduction | p. 1 |
Background | p. 1 |
Characteristics of the F-22A | p. 1 |
History of the F-22A Program | p. 1 |
Aircraft Production | p. 2 |
Procurement History | p. 2 |
Purpose of This Monograph | p. 3 |
Shutdown | p. 3 |
Shutdown and Restart | p. 4 |
Warm Production | p. 4 |
Continued Production | p. 5 |
Our Research Methodology | p. 5 |
Research Factors | p. 6 |
Organization of the Monograph | p. 7 |
Shutdown and Restart Cost Estimates | p. 9 |
Types of Cost and Profit | p. 10 |
Activities Are Tied to Production Profiles | p. 11 |
Types of Activities | p. 11 |
Shutting Down and Restarting the Production Line | p. 13 |
Termination | p. 14 |
Hiatus | p. 21 |
Restart | p. 25 |
Summary | p. 31 |
Production Cost Estimate | p. 33 |
Airframe Contractors Target Price Curve and Propulsion Costs | p. 33 |
Overview of TPC and Propulsion Model | p. 34 |
Effects of Changing Annual Procurement Rate | p. 35 |
Selecting the Portion of the Original Curve | p. 36 |
Effects of Restarting the Production Line | p. 37 |
Tail-Up and Last-Lot Rate Effects | p. 39 |
Results of the Production Model | p. 39 |
Munitions, Support, Sustainment, Spares, and Logistics | p. 41 |
PALS | p. 43 |
Airframe Nonrecurring | p. 43 |
Engine Nonrecurring | p. 43 |
PSAS (PSS and PSP) | p. 43 |
PSO | p. 44 |
OGC | p. 44 |
Engine Support | p. 44 |
Useful Loads | p. 45 |
Costs Incurred During Hiatus or After Termination | p. 47 |
Extending the Forecast | p. 49 |
Summary | p. 52 |
Sustainment, Modernization, Technical Data Package, and Contract Closeout | p. 55 |
Sustainment | p. 55 |
Modernization | p. 59 |
Technical Data Package | p. 61 |
Contract Closeout | p. 63 |
Summary | p. 65 |
The Effect of the Production Gap on Vendors | p. 67 |
The Vendor Assessment Survey | p. 67 |
Sampling Approach | p. 68 |
Caveats | p. 69 |
The F-22A Industrial Base | p. 69 |
F-22A Vendor Participation with the F-35 Program | p. 71 |
Assessment of Supplier Effects from a Production Gap | p. 72 |
Vendor Issues Caused by a Production Gap | p. 73 |
Vendor Requalification | p. 74 |
Conclusion | p. 75 |
Summary and Policy Options for the Air Force | p. 77 |
Cost Estimates | p. 77 |
Options for the Air Force | p. 78 |
Shutdown | p. 78 |
Shutdown and Restart | p. 78 |
Warm Production | p. 79 |
Continued Production | p. 79 |
Sustainment and Modernization Program | p. 79 |
Technical Data Package and Contract Closeout | p. 80 |
Industrial Base Implications | p. 80 |
Appendixes | |
Vendor Assessments | p. 83 |
Previous RAND Research on Shutdown and Restart | p. 89 |
Original and Restart Learning Curve Slopes | p. 93 |
Bibliography | p. 95 |
Table of Contents provided by Ingram. All Rights Reserved. |
The New copy of this book will include any supplemental materials advertised. Please check the title of the book to determine if it should include any access cards, study guides, lab manuals, CDs, etc.
The Used, Rental and eBook copies of this book are not guaranteed to include any supplemental materials. Typically, only the book itself is included. This is true even if the title states it includes any access cards, study guides, lab manuals, CDs, etc.